Village of Wind Point issued the following announcement on June 9.
Work began on the new pathway at the Wind Point Lighthouse today. Below is a tentative schedule for the work.
June 8-10 Path Excavation
June 11- Prep for Concrete Installation
June 14- Concrete Installed
June 11-15- Stone placed for asphalt
June 17-18- Asphalt Pavement installation
June 21-25- Restoration and Fence Repair
June 28- Final inspection.
Once complete the pathway, which will be separate from the driveway and parking area, will provide a safe option for pedestrians and bicyclists to use. The pathway will provide direct connections to the south lawn, lakefront and existing walkways.